Wednesday, 29 February 2012

Tiling.

We went past the house last night, and found that they have done majority of the tiling in one day! They have also began painting the render on the exterior! They have also installed the light fixtures, and the switches!!!


Things left for builders to do:
  • Install black glass splashback.
  • Grout tiles.
  • Paint remainder of the render. 
  • Install doors/handles.
  • Paint front door.
  • Install garage door.
  • Lay carpets.
  • Clean up. 
I'm pretty sure, that's all they have left to do. Then we get started on landscaping!








Thursday, 23 February 2012

Painting.

We went back to the house on Wednesday, to find that all (but the kitchen) has been painted. We've now got all the tiling done in the bathrooms/laundry, all the rooms painted, shelves in the cupboards/pantry and mirror doors on our built-in wardrobes! We have been told, that we are looking at Friday 30th March as our hand over date, but will be confirmed on Monday! Can't wait. Have a look at the photos of the paint work, below:

Feature Wall :) Solver: Kanga

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini
and Mirror Doors on Built-in Robes!

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Paintwork - 1/2 Strength AVJ Scallopini

Wednesday, 15 February 2012

Paint & Benchtops

We went back to the house yesterday, to meet up with our landscapers from Gardens Etc. so we could walk out where and how we wanted our landscaping to be. We are so excited with what we have come up with! We also had a look and the Caesarstone benchtops have been installed, along with the roof being painted and a border of colour on the walls! Take a look:









Sunday, 5 February 2012

New hand-over date.

Nathan got a phone call today from the builders and they have informed us that we will now recieve the keys in the third week of March instead of early April! That's next month!!!!!

Wednesday, 1 February 2012

TILES!

There aren't many photos of this because we can't actually get into our house. But they have done all the tiling in the laundy (shown in picture), bathroom and ensuite! We are having these tiles throughout the whole house. I can't wait to share more photos with you and sorry about the lack of photos in this post. But stay posted, there will be more!

Laundry tiling.